Project Overview

The Suraj Complex Redevelopment Project represents a bold vision for the future of our community. This comprehensive initiative aims to transform our existing infrastructure into a state-of-the-art residential complex that meets the evolving needs of our residents while preserving the community spirit that makes Suraj Complex special.

Our redevelopment plan focuses on sustainable design, modern amenities, enhanced security, and improved quality of life for all residents. The project includes complete reconstruction of buildings, addition of new facilities, and implementation of smart home technologies.

2023

Project Initiation

Feasibility study and initial planning phase completed

2024

Design & Approval

Architectural designs finalized and regulatory approvals obtained

2025

Construction Phase

Ground breaking and main construction activities

2026

Completion

Project completion and resident relocation

Redevelopment Plan

Redevelopment Committee

Dedicated team overseeing the redevelopment project

Member Role Responsibility Contact
Mr. Rajesh Sharma
Chairman Overall project supervision and decision making chairman@surajcomplex.com
Mrs. Priya Patel
Secretary Documentation and coordination secretary@surajcomplex.com
Mr. Vikram Singh
Technical Head Technical oversight and quality control technical@surajcomplex.com
Mr. Amit Desai
Finance Budget management and financial planning finance@surajcomplex.com
Mrs. Anjali Reddy
Legal Advisor Legal compliance and documentation legal@surajcomplex.com
Mrs. Sunita Menon
Resident Representative Resident concerns and feedback residents@surajcomplex.com

Project Progress

Track the redevelopment project milestones and completion status

Planning & Design

100%

Architectural designs, engineering plans, and regulatory approvals completed.

Foundation Work

75%

Excavation and foundation construction in progress. Expected completion Q2 2024.

Structural Work

40%

Superstructure construction underway for Phase 1 buildings.

Utilities & Services

20%

Planning and preliminary work for electrical, plumbing, and HVAC systems.

Interior Finishing

0%

Interior work to begin after structural completion. Scheduled for Q4 2024.

Landscaping & Amenities

0%

External development including gardens, parking, and recreational facilities.